JLR MELKSHAM WEEK 31 – LET THERE BE LIGHT

With a list of hurdles being thrown at us stopping us connect the mains electricity we have been able to hijack the temporary builders supply to allow the lights to finally be switched on… although not all at the same time. It’s fabulous to see the building slowly coming to life and the lights make a huge difference.

In the workshop the tilers have been motoring on with almost half the workshop tiled and grouted. Again it makes a huge difference to the space and really gives you a sense that we are tantalisingly close to the finish line.

 

Outside the cladding is almost complete with the very big signage workmarks and logos taking centre stage on both the front and rear elevations.

Elsewhere the tiling has also started in the showroom with the marmite ‘walnut’ effect tiling to the customer core area being the first to go down.

With all the detailing and sub-contractor design elements agreed it’s now a sprint to the finish for the main contractor and with only 10 full weeks until handover the finishing trades are going to be working hard.